Monday, 11 April 2011
More Successful Projects for IQA
Glenfinnan Rd, Glasgow
IQA has successfully completed four more MSF projects: 60, 61, 80, and 110 Glenfinnan Road, Glasgow. Each block consisted of 56 domestic dwellings and commenced in 2010 with an approximate duration of 3 months per block. The changeovers were completed over a four day period with one block completed each day, totaling 224 renewed supplies. IQA liaised with the Cube Housing Association and concierge to ensure our customer’s requirements and considerations were met throughout the projects.
Drygate, Glasgow
A further two MSF projects have been successfully completed at 24 and 36 Drygate, Glasgow. These blocks had 72 and 84 domestic dwellings respectively and each project was completed in approximately 5 months. The changeovers were completed over a two day period with one block completed each day, giving a total 156 renewed supplies. IQA liaised with GHA and the concierge to ensure our customer’s requirements and considerations were met throughout the projects.
Monday, 21 March 2011
Quality System Auditor
Monday, 7 March 2011
"The Towers" Changeover
Thursday, 17 February 2011
IQA Property

Wednesday, 16 February 2011
Training Report
David McKinlay Training and Compliance Manager
A total of 33 personnel, including 2 new members of staff, passed through the instruction rooms in Paisley and Liverpool in January 2011.
The topics covered were refresher, final interview and authorisation preparation as well as reporting procedures and metering instruction.
On 14th January a total of 6 operatives successfully completed their OP3 refresher course while one of our jointing resources successfully passed his LV live working refresher training on 25th January. 6 operatives all attended and successfully completed the M0008 five day course between 24th-28th January with their final OP3 interviews being passed. A further 2 operatives successfully completed their WI1 initial safety induction course on 31 January and will now work towards their W1 final interview with SP Compliance.
Friday, 4 February 2011
Another Successful Project ahead of schedule
Edgefauld Rd, Springburn, GlasgowBrian Ward, Electrical Operations Manager (Scotland)
IQA has completed the first multi story flat project of 2011, modernising the supply to 100 customers on Scottish Power’s Internal Mains Network. The duration of this project was 4 months beginning in October 2010. All 100 customers had their electricity supplies successfully changed over a 2 day period, with 50 properties being completed each day.
Wednesday, 2 February 2011
New Contract Award
An 18 month contract has been awarded to IQA by Scottish Power for the Provision of Internal Mains and Services.
The contract, covering both SP Scotland and SP Manweb, commences on 6th January 2011 and continues until 30th June 2012, at which point a potential 30 month contract extension may be agreed.
This very positive news for IQA is a great start to 2011 and allows the Company to grow and support our future strategic plans.